Four-apartment home in Günzburg installed in four days with Glatthaar Systembau

Glatthaar Systembau has completed the precast concrete structure of a new residential building in Günzburg, Germany. The building has four apartments sharing a common staircase, spread over a ground floor, upper floor and attic floor, with 235 m² of floor space. Glatthaar first built a new basement ceiling slab, including cantilevers and foundation work. The team then installed the entire structure above in just four days. That took 1,916 m² of precast concrete and 9,711 kg of steel reinforcement, made up of:

  • 101 solid 12 cm wall panels
  • 30 solid 20 cm floor and ceiling slabs, some weighing almost 10 tonnes
  • one precast staircase

Electrical boxes and conduits were fitted at the factory. Eight thermally insulated brackets were cast into the ground-floor ceiling so two steel balconies can be added later. Glatthaar handled the project from structural design to final installation, and the elements went up from ground floor to roof without a break and with no concrete poured on site.